Underfall Yard sluice repairs, phase 4, go to Qualter Hall
- Bristol City Council
- South West
- Below threshold - without competition
- 10 September 2026 to 8 October 2026
Bristol City Council hired Qualter Hall & Co Ltd for the fourth phase of repairs to the sluice gates at Underfall Yard. The historic gates and their culverts control water levels in Bristol Harbour and are part of the city's flood defences.
The council awarded the work directly, without a competition, in September 2026. The £60,000 contract was due to end in October 2026.
- What
- Flood defence and flood alleviation works
- Buyer
- Bristol City Council
- Supplier
- Qualter Hall & Co Ltd
- Value
- £60,000
- How it was bought
- Below threshold - without competition
- Dates and next
- Sep 2026 to Oct 2026