MSH Building replaces curtain walling at Caerphilly's St. Martins school
- Caerphilly County Borough Council
- Wales
- Open
- 20 July 2026 to 28 August 2026
Caerphilly County Borough Council hired MSH Building Ltd to replace the curtain walling at St. Martins Comprehensive School during the summer holidays.
The new curtain wall, door and high-level windows were to follow a Technal specification. The works also took in new cladding, a replacement suspended ceiling, making good the floors and mechanical and electrical work. Everything was planned for the six-week break and had to be finished before students came back.
Price was the only scoring criterion. The council awarded the £179,271 contract in May 2026, below its £250,000 estimate, and the works were due to end in August 2026.
- What
- Curtain walling, rooflights and atrium glazing
- Supplier
- MSH Building Ltd
- Value
- £179,271
- How it was bought
- Open
- Dates and next
- Jul 2026 to Aug 2026