Earl Mortimer College's glazed atrium works go to S C Joseph
- Herefordshire Council
- West Midlands
- Limited, 2 bids
- 2 June 2026 to 28 August 2026
Herefordshire Council hired S C Joseph Ltd to carry out glazed atrium works at Earl Mortimer College and Sixth Form.
The job covered structural glazing for the college's atrium, along with the framing and finishing work needed to complete it.
Two bids were received, and S C Joseph won at £37,387 in May 2026. The works were due to end in August 2026.
- What
- Curtain walling, rooflights and atrium glazing
- Supplier
- S C Joseph Ltd
- Value
- £37,387
- How it was bought
- Limited
- 2 bids
- Dates and next
- Jun 2026 to Aug 2026