A396 Stoke Woods retaining wall built for Devon by Macplant Construction
- Devon County Council
- South West
- Call-off
- 5 August 2026 to 7 December 2026
Macplant Construction Ltd is building a retaining wall to stabilise the A396 at Stoke Woods, near Stoke Cannon, for Devon County Council.
The wall is reinforced concrete, held in place by piles and anchors. The job also covers new kerbs, road lining and surfacing.
The council ordered the work under lot 5 of its own Minor Engineering Works Framework Contract 2026-2030, after asking for quotations. Macplant, a small business, took the £908,006 order, with work running from August to December 2026.
Contract ends December 2026
- What
- Retaining walls, slope stabilisation and land hazard works
- Buyer
- Devon County Council
- Supplier
- Macplant Construction Ltd
- Value
- £908,006
- How it was bought
- Call-off, Minor Engineering Works Framework Contract 2026-2030
- Dates and next
- Aug 2026 to Dec 2026