Contract awardedLocal area energy planning and energy infrastructure feasibility

City Science draws up detailed design for the Durham City Heat Network

Durham County Council hired City Science Corporation Limited to produce the detailed design for phase 2 of the Durham City Heat Network.

The council had recently received funding to take the heat network on to detailed design. That followed feasibility work paid for by grant funding from the Heat Networks Delivery Unit. The design was to give the project a timeline with milestones, a resource and budget plan and a risk management plan. City Science was also to set out goals and scope and engage partners in the area.

City Science, a small business, was awarded the £120,000 contract directly. The work started in April 2026 and was due to end in October 2026.

What
Local area energy planning and energy infrastructure feasibility
Value
£120,000
How it was bought
Below threshold - without competition
Dates and next
Apr 2026 to Oct 2026

How it was bought

1 official notice
  1. 30 Apr 2026Contract starts
  2. 3 Jun 2026Award noticeFind a Tender
  3. 31 Oct 2026Contract ends

How it compares

With every local area energy planning and energy infrastructure feasibility award since 2021

Half of awards fall between £45,000 and £167,456Median £80,000

Awards
404
Firms that won them
175
Median award
£80,000
of 385 with a value
This award
Bigger than 65%
of them
Typical length
6 months
In North East
15 awards

City Science Corporation Limited ranks 7th of 175 firms for local area energy planning and energy infrastructure feasibility awards since 2021.

RankFirmAwardsValue
1Locked32£13.3m
2Locked27£5.41m
3Locked17£5.05m
4Locked16£2.68m
5Locked14£5.4m
6Locked13£1.03m
7City Science Corporation Limited Won this one11£1.33m
See who wins this work

Figures to 25 November 2026

Local area energy planning and energy infrastructure feasibility at other buyers

Durham County Council has awarded 2,031 contracts since 2021.

See Durham County Council's page

3 local area energy planning and energy infrastructure feasibility tenders are open now

See them
More local area energy planning and energy infrastructure feasibility contracts awarded in 2026