Dormanstown Depot microgrid feasibility study goes to Decerna
- Redcar and Cleveland Borough Council
- North East
- Direct award
- 2 January 2026 to 2 April 2026
Redcar and Cleveland Borough Council commissioned Decerna Limited to study whether a microgrid at Dormanstown Depot would be feasible.
The study was a standalone piece of work on a proposed microgrid at the one depot site. The council awarded it directly, under an exemption. The £45,000 contract ran for three months from January 2026.
- What
- Local area energy planning and energy infrastructure feasibility
- Supplier
- Decerna Limited
- Value
- £45,000
- How it was bought
- Direct award
- Dates and next
- Jan 2026 to Apr 2026