A22 junction design for East Sussex County Council comes from Jacobs
- East Sussex County Council
- South East
- Call-off from a framework agreement
- 1 April 2025 to 31 December 2025
East Sussex County Council needed a detailed design for improvements to five A22 junctions around South Wealden and Eastbourne. The DfT funded the A22 Corridor Package in 2024, with construction subject to its approval of a Full Business Case.
That business case had to include an accurate price for the works, and a contractor needed a detailed design to price them. Jacobs wrote the outline business case and was already producing the full one under a direct award from September 2024. The council judged it best placed to do the design.
Jacobs was awarded the design directly through the Crown Commercial Service's Construction Professional Services framework (RM6165). The target price under the NEC4 contract was £3,175,740. The work started in April 2025 and was due to end in December 2025.
- What
- Highway and traffic engineering design
- Supplier
- Jacobs
- Value
- £3.18m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Apr 2025 to Dec 2025