Contract awardedReservoir and dam engineering
Bruton Dam MIOS works design for the Environment Agency goes to Jacobs
- Environment Agency
- South West
- Call-off from a framework agreement
- 16 February 2026 to 15 February 2027
The Environment Agency ordered the detailed design for the MIOS works at Bruton Dam from Jacobs. The job is engineering design for the dam, and Jacobs has 12 months to deliver it.
The agency placed the order through a framework in February 2026, at £298,741. The contract runs to February 2027.
Alert me to similar tenders
Contract ends February 2027
- What
- Reservoir and dam engineering
- Buyer
- Environment Agency
- Supplier
- Jacobs
- Value
- £298,741
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2026 to Feb 2027