Garstang Gate Repair Phase 3b for Environment Agency goes to JBA Bentley
- Environment Agency
- North West
- Call-off
- 30 March 2026 to 30 September 2026
The Environment Agency ordered phase 3b of the Garstang Gate repair from JBA Bentley Ltd.
The repair was to a gate at Garstang, in Lancashire, that forms part of the agency's flood defences. It was ordered through the agency's own Asset Operation, Maintenance and Response Framework.
The £386,163 contract was due to run from March to September 2026.
- What
- Flood defence and flood alleviation works
- Buyer
- Environment Agency
- Supplier
- JBA Bentley Ltd
- Value
- £386,163
- How it was bought
- Call-off, Asset Operation, Maintenance and Response Framework
- Dates and next
- Mar 2026 to Sep 2026