Strategic Valves Installation Project gets site supervision from Yorath
- University of Exeter
- South West
- Below threshold - without competition
- 15 May 2026 to 14 May 2027
The University of Exeter hired Yorath Engineering Limited to act as clerk of works on its Strategic Valves Installation Project.
Yorath supervises work on site and compiles the quality assurance pack. The firm also deals with the contractors, handles RO/NRO authorisations and passes as-fitted details to the network designer so the gas drawings can be updated.
The university awarded the work directly in May 2026, without a competition. The award notice gives £17,518 and a later contract details notice gives £25,757. The contract runs to May 2027.
Contract ends May 2027
- What
- Clerk of works and site supervision
- Buyer
- University of Exeter
- Supplier
- Yorath Engineering Limited
- Value
- £17,518
- How it was bought
- Below threshold - without competition
- Dates and next
- May 2026 to May 2027