External fire safety consultancy for Hackney goes to Airey Miller
- London Borough of Hackney
- Call-off, 1 bid
- 16 August 2026 to 18 August 2030
London Borough of Hackney has hired Airey Miller as specialist consultant on its external fire safety remedial works. The council ordered the work directly through The Hyde Group's Building and Fire Safety Framework (ECH 1131).
The £9m contract matched the council's estimate. It was awarded in August 2026 and runs for four years, to August 2030.
Contract ends August 2030
- What
- External wall fire risk appraisals (FRAEW and EWS1)
- Supplier
- Airey Miller
- Value
- £9m
- How it was bought
- Call-off, The Hyde Group
- 1 bid
- Dates and next
- Aug 2026 to Aug 2030