Stantec designs Pulens Lane bridge replacement for Hampshire council
- Hampshire County Council
- South East
- Call-off
- 16 February 2026 to 27 November 2026
Hampshire County Council appointed Stantec to design a replacement for Pulens Lane bridge, whose troughing deck is in poor repair. The design may be a new structure or a new deck.
The council wants the bridge work to fit a carriageway improvement scheme that narrows the road and adds a cycleway. Stantec first produces an optioneering report, then takes the design through its later phases.
The council ordered the work from Lot A of the PCI framework, which it runs itself. The £49,323 contract started in February 2026 and is due to end in November 2026.
Contract ends November 2026
- What
- Bridge and structures inspection, assessment and design
- Supplier
- Stantec
- Value
- £49,323
- How it was bought
- Call-off, PCI
- Dates and next
- Feb 2026 to Nov 2026