Capgemini migrates and retires HMRC's legacy data warehouses for DWIT
- HM Revenue & Customs
- Call-off from a framework agreement
- 20 July 2026 to 19 July 2031
HM Revenue & Customs hired Capgemini to migrate and decommission its legacy data warehouses, under lot 2 of DWIT.
The job is to shift the warehouses' data, services and users onto the planned DWIT architecture safely, keeping disruption to HMRC's business low. Capgemini works alongside the Service Integrator and the Lakehouse and Feed Factory suppliers.
HMRC ordered the work as a call-off under a framework agreement, and the £200m contract was awarded in June 2026. It runs for five years, to July 2031.
Contract ends July 2031
- What
- Data migration and extraction
- Buyer
- HM Revenue & Customs
- Supplier
- Capgemini
- Value
- £200m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jul 2026 to Jul 2031