Western Hanger apron at Milford Haven Port Authority replaced by Austwel
- Milford Haven Port Authority
- Wales
- Open
- 1 November 2025 to 1 January 2026
Milford Haven Port Authority hired Austwel to replace a broken section of concrete apron outside the Western Hanger, a historic listed hangar built for Sunderland planes.
Rebar was showing through the damaged concrete. Austwel had to lift the section in front of the hangar doors, lay new concrete and take all waste away for sustainable disposal.
The £84,057 contract followed an open tender. It started in November 2025 and was due to end in January 2026.
- What
- Airfield pavements, runways and ground lighting
- Supplier
- Austwel
- Value
- £84,057
- How it was bought
- Open
- Dates and next
- Nov 2025 to Jan 2026