FCCS design and validation for Network Rail comes from AtkinsRéalis
- Network Rail Infrastructure Limited
- Direct award
- 13 July 2026 to 13 June 2028
Network Rail Infrastructure Limited hired AtkinsRéalis for the final stage of design and validation work on Project FCCS T190Plus.
The work includes BIM-aligned templates that enable CCS, work instructions and templates covering Early Release and Shadow Mode (MVP), and supporting system safety documents. AtkinsRéalis also acts as technical lead and checks FCCS deliverables already produced.
Network Rail awarded the work directly, without competition, in May 2026. Spending is tied to set milestones and paid on time and materials, capped at £817,782. The contract runs to June 2028.
Contract ends June 2028
- What
- Rail infrastructure design and technical consultancy
- Supplier
- AtkinsRéalis
- Value
- £817,782
- How it was bought
- Direct award
- Dates and next
- Jul 2026 to Jun 2028