Heaton Depot feasibility study for Northern Trains goes to Ramboll
- Northern Trains Limited
- Yorkshire and the Humber
- Below threshold - open competition
- 2 June 2026 to 30 November 2026
Northern Trains Limited hired Ramboll to find the best way to deal with issues found at Heaton Depot.
Surveys, a feasibility report and a constructability assessment come first. Ramboll must then appraise the options, get stakeholders to agree in principle on a single preferred one, and produce a preliminary design for it. The study also has to deliver a specification of requirements for the later design-stage tender.
Ramboll was appointed after an open competition in which quality counted for 55% of the score, price 40% and social value 5%. The £261,000 contract matches the estimate and runs from June 2026 to November 2026 under a JCT Consultancy Agreement.
Contract ends November 2026
- What
- Rail infrastructure design and technical consultancy
- Supplier
- Ramboll
- Value
- £261,000
- How it was bought
- Below threshold - open competition
- Dates and next
- Jun 2026 to Nov 2026