Heaton reception roads: Northern Trains wants design and upgrade works
- Northern Trains Limited
- North East
- Below threshold - open competition
- 18 December 2026 to 30 July 2027
Northern Trains Limited wants a contractor to design and build improvements to the reception roads at Heaton. The work covers Reception Roads 1, 2, 3 and 4 and Siding A, and aims to make train servicing more resilient so the timetable can be kept. Most of the work is civil, mechanical and electrical, and it must follow Network Rail Technical Approval Standards.
Price counts for 55% of the score and quality for 45%. The work is estimated at £641,170. The deadline for bids is 20 November 2026, and the contract runs to July 2027.
Closed 20 Nov 2026
- What
- Railway track and civils
- Estimated value
- £641,170
- How it is being bought
- Below threshold - open competition
- Bids due
- 20 Nov 2026
- Contract dates
- Dec 2026 to Jul 2027