Network Rail signs agreement for Middlesbrough Station's new Platform 3
- Tees Valley Combined Authority
- North East
- Direct award
- 29 July 2026 to 31 March 2027
Tees Valley Combined Authority (TVCA) signed a Basic Implementation Agreement with Network Rail Infrastructure Limited for a new Platform 3 at Middlesbrough Station. The platform is Work Package 3 of the Middlesbrough Station Improvement Programme, covering rail infrastructure and the engineering needed to deliver it.
TVCA awarded the £3.3m agreement directly to Network Rail and signed it in June 2026. It runs to March 2027.
Contract ends March 2027
- What
- Railway track and civils
- Value
- £3.32m
- How it was bought
- Direct award
- Dates and next
- Jul 2026 to Mar 2027