Environmental Chamber Module 4 at NPL is surveyed by Megan Mechanical
- National Physical Laboratory
- London
- Below threshold - unknown
- 8 July 2026 to 8 July 2026
Megan Mechanical Services Ltd was hired to survey and test Environmental Chamber Module 4 at the National Physical Laboratory (NPL) and the chamber's building services. From those findings, the firm was to draw up a detailed design and a cost plan for upgrading the chamber later.
The job covered surveys and design only, with no building work or new equipment at this stage. The £4.04m contract started in July 2026.
- What
- Building services (M&E) engineering design
- Supplier
- Megan Mechanical Services Ltd
- Value
- £4.04m
- How it was bought
- Below threshold - unknown
- Dates and next
- Jul 2026 to Jul 2026