Dounreay LLW vault backfill Stage 3a goes to John Gunn & Sons
- Nuclear Restoration Services
- Scotland
- Below threshold - without competition
- 20 July 2026 to 30 September 2026
Nuclear Restoration Services hired John Gunn & Sons Ltd to backfill the outside of the low level waste (LLW) vault at Dounreay. The job was Stage 3a of that backfill.
The £28,183 contract was awarded directly, without a competition. Work started in July 2026 and was due to end in September 2026.
- What
- Groundworks, enabling works and site infrastructure
- Supplier
- John Gunn & Sons Ltd
- Value
- £28,183
- How it was bought
- Below threshold - without competition
- Dates and next
- Jul 2026 to Sep 2026