Air source heat pump for the Grange at Sir Roger Manwood's School
- Sir Roger Manwood's School
- Open procedure
- 21 December 2026 to 31 March 2027
Sir Roger Manwood's School wants a contractor to design and fit an air source heat pump system to heat the Grange. The heat pumps would be the building's only source of heat and should run efficiently for at least 20 years. The work includes groundworks, taking out the old plant, linking the new system to existing secondary systems and the customer's share of the DSO upgrade works.
Technical quality counts for 60% of the score and price for 40%. The school first estimated the work at £215,000 and later revised the estimate to £178,000.
The deadline for bids is 13 December 2026. The work is due to finish by March 2027.
Closes in 22 days· 13 Dec 2026
- What
- Heat pumps
- Estimated value
- £215,000
- How it is being bought
- Open procedure
- Bids due
- 13 Dec 2026
- Contract dates
- Dec 2026 to Mar 2027