The South East Wales Corporate Joint Committee hired AECOM to study where waste heat could be used for heat networks.
Waste heat opportunities identified in the Local Area Energy Plans (LAEPs) are the starting point. AECOM is narrowing these to three viable sites, then carrying out a high-level feasibility study on them. The study looks at whether each site could go ahead with low-carbon heat sources.
The committee chose AECOM after a limited competition. The £28,198 contract runs from September 2026 to December 2026.
Contract ends December 2026
- What
- Local area energy planning and energy infrastructure feasibility
- Supplier
- AECOM
- Value
- £28,198
- How it was bought
- Below threshold - limited competition
- Dates and next
- Sep 2026 to Dec 2026