Wolviston cycleway for Stockton-on-Tees goes to Story Contracting
- Stockton-on-Tees Borough Council
- North East
- Call-off
- 14 October 2026 to 26 March 2028
Stockton-on-Tees Borough Council has hired Story Contracting to build the Cowpen Bewley Woodland Park to Wolviston Cycleway.
The contract has two stages. The first stage covers early contractor involvement and pricing. Construction makes up the second stage, planned for April 2027 to March 2028 and to be confirmed during the first.
The council ordered the work through the NEPO211 Civil Engineering & Infrastructure Works framework, at £78,369.
Contract ends March 2028
- What
- Footways, cycleways and path construction
- Supplier
- Story Contracting
- Value
- £78,369
- How it was bought
- Call-off, Civil Engineering & Infrastructure Works
- Dates and next
- Oct 2026 to Mar 2028