Arup designs moveable shielding concept for the STEP fusion plant
- UK Fusion Energy Ltd
- Below threshold - unknown
- 28 October 2026 to 25 February 2027
UK Fusion Energy Ltd has appointed Arup to produce a concept design study for moveable shielding at the STEP Prototype Power Plant. UKFE leads STEP, the programme designing and building a prototype fusion plant at West Burton in Nottinghamshire. It would be the UK's first.
UKFE picked Arup after an open competition advertised on Find a Tender and its Delta portal, in October 2026. The £70,000 contract can run to April 2027 with a two-month extension.
Contract ends February 2027
- What
- Nuclear technical support, engineering and safety
- Buyer
- UK Fusion Energy Ltd
- Supplier
- Arup
- Value
- £70,000
- How it was bought
- Below threshold - unknown
- Dates and next
- Oct 2026 to Feb 2027
- Being re-tendered now