Contract awardedStandby generators and UPS
Centiel replaces the 200KVA UPS at The Walton Centre NHS Foundation Trust
- The Walton Centre NHS Foundation Trust
- North West
- Direct
- 2 March 2026 to 10 August 2026
The Walton Centre NHS Foundation Trust paid Centiel UK Ltd to replace its 200KVA uninterruptible power supply (UPS), a job the trust called critical.
The work covered taking out the old equipment and installing and commissioning a new UPS to keep power running for hospital operations. The trust awarded the £122,989 contract directly. Work was due to run from March to August 2026.
- What
- Standby generators and UPS
- Supplier
- Centiel UK Ltd
- Value
- £122,989
- How it was bought
- Direct
- Dates and next
- Mar 2026 to Aug 2026