Brocastle's extra 25 MVA connection offer comes from National Grid
- Llywodraeth Cymru / Welsh Government
- Wales
- Below threshold - without competition
- 10 August 2026 to 31 March 2027
Llywodraeth Cymru / Welsh Government is buying a connection offer from National Grid to bring an extra 25 MVA of power to Brocastle, Bridgend. The offer is with the distribution network operator for South Wales.
Alongside the offer, the work includes a modification application to the National Energy System Operator (NESO) and an assessment of the effect on the transmission system.
The Welsh Government awarded the £28,260 contract directly, without a competition. It runs from August 2026 to March 2027.
Contract ends March 2027
- What
- Electricity network works and connections
- Supplier
- National Grid
- Value
- £28,260
- How it was bought
- Below threshold - without competition
- Dates and next
- Aug 2026 to Mar 2027