Brocastle Power 25 MVA network works go to NGED
- Llywodraeth Cymru / Welsh Government
- Wales
- Open, 1 bid
- 1 October 2026 to 1 February 2035
Llywodraeth Cymru / Welsh Government needs non-contestable electricity network works for Brocastle Power, identified at 25 MVA. National Grid Electricity Distribution (NGED) SW PLC is the distribution network operator for the area, and the government says it is the only supplier able to do them.
The government awarded NGED the £600,000 contract directly in October 2026. It can run to October 2036 with an extension of up to 20 months.
Contract ends February 2035
- What
- Electricity network works and connections
- Value
- £600,000
- How it was bought
- Open
- 1 bid
- Dates and next
- Oct 2026 to Feb 2035
- Option to Oct 2036