Great Yarmouth railway station feasibility study goes to Holder Mathias
- Great Yarmouth Borough Council
- East of England
- 17 March 2026 to 30 May 2026
Great Yarmouth Borough Council commissioned Holder Mathias LLP to study how Great Yarmouth railway station could be improved and refurbished.
The study was carried out with Greater Anglia. It also took a wider look at the station site and the development opportunities emerging around it.
Holder Mathias was awarded the £30,000 contract in March 2026, and the work was due to finish in May 2026.
- What
- Rail infrastructure design and technical consultancy
- Supplier
- Holder Mathias LLP
- Value
- £30,000
- How it was bought
- Not published
- Dates and next
- Mar 2026 to May 2026